Turnkey project to design, construct and commission the combined
fuel and raw materials handling and storage plant for the new
Rugby Cement Works. The plant was designed to receive and reclaim
1500t coal, 1700t pet coke, 8000t clay, 200t oxide and 1200t sand
in order to provide fuel and raw materials to the new kilns.
|